Project overview
SoftBank/Nvidia — Sakai, Japan is a under construction AI or hyperscale datacenter project associated with SoftBank / Nvidia in Osaka, Japan. Public sources describe up to 300 MW of planned capacity. Reported completion timing is 2026.
Location and surrounding area
SoftBank/Nvidia — Sakai, Japan is mapped at 34.5733, 135.4830 near Osaka, Japan. Nearby infrastructure and environmental features are presented separately as geographic context. Proximity does not establish facility use, dependency, or impact.
Area and infrastructure context
Nearby features provide geographic context. Proximity alone does not show that this facility uses, affects, or depends on a resource.
Nearest tracked place: Sakai, 32 (JP) (1.8 km)
- Grid infrastructure
- 堺港火力発電所, 2.8 km away; 72 mapped within 25 km
- Surface water
- 内川, 0 km away; 439 mapped within 25 km
- Power generation
- 堺港火力発電所, 2.8 km away; 66 mapped within 25 km